fiz;s]
lkfFk;ks] foxr dqN
lkyksa ls ;g ik;k x;k gS fd laj{kk iwoZd xkM+h ifjpkyu gsrq laj{kk ds tks fu;e
cus gS mu fu;eksa dks njfdukj ,oa utjkUnkt djrs gq, {ks=h;@eMayh; Lrj ij] laj{kk vf/kdkjh dks fo”okl esa fy,
fcuk gh] JPO cuk fn;k tkrk gSA fu;e ds fo:/k dk;Z djk;k tkrk gS vkSj tc vlkekU;
?kVuk ?kVrh gS rks fu;e dks fn[kkrs gq, deZpkjh dks nks’kh djkj fn;k tkrk gS
vkSj n.nkRed dk;Zokgh fd;k tkrk gSA tcfd JPO cukusokys vf/kdkjh fdlh u fdlh cgkus mrjnkf;Ro ls eqDr gks tkrs gSaA
jsyos cksMZ ls fuxrZ funsZ”k dh Hkh Missinterpetition fd;k tkrk gS voS/k BPC okyh xkMh dk ifjpkyu fd;k tkrk gSA xyr rjhds ls GDR
cukus dk funsZ”k fn;k tkrk gSA fcuk xst dk LVscy yksM Dyh;j
djus dk ncko fn;k tkrk gS tks Crew
fu;e iwoZd dk;Z
djuk pkgrk gS mls xkMh foyEcu ,oa nwljs ds dke esa n[kykUnkth djus dk vkjksi
yxkrs gq, n.MkRed dk;Zokgh fd;k tkrk gSA voS/k BPC dh xkM+h ds ifjpkyu ,oa GDR ds lEcU/k esa iz”u ds lkFk mldk mRrj nsrs gq, vki dks laf{kIr
tkudkjh nsus dk iz;kl fd;k tkrk gS tks fuEufyf[kr gSA
Quiries On GDR
&Running with Invalied BPC
Q. 1. In which Conditions/ when & where GDR
should be performed ?
Ans :-
,sls LVs”ku]
tgkaW TXR miyC/k ugha gS vkSj C & W LVkQ Hkh ugha gS] oSls LVs”ku ij yksfMx@vuyksfMax ds ckn ;k Stable
Load, ftldk BPC
invalid gS] Dyh;j djrs le; ;k xkM+h izLFkku ds iwoZ xkMZ &yks- ik- }kjk xkMh dk tkaWp fd;k tk,xkA rhu
izfr esa tkaWp fjiksVZ cuk;k tk,xk vkSj LVs”ku ekLVj dks fn;k tk,xkA blds fy,
fuEufyf[kr fu;e ,oa funsZ”k gSaA
1-
fnukad 31@07@2001
ds j-s cks- dk i=kad % 2000/Safety/ (A & R)19/35 dk ikjk &2 rFkk 2(iii)
2-
G& SR dk C.S. No. 6 ds vUrxrZ fu;e 4-31-2] fnukad 31-07-01
3-
fnukad 8/2/06 ds jsYos cksMZ dk i=kad % 2005/M(N)
951/13
4-
fnukad 7/3/06 ds jsYos cksMZ dk i=kad % 2005/M(N)
951/13
5-
fnukad 28/8/09 ds jsYos cksMZ dk i=kad % 2005/M(N) 951/13
6-
fnukad 29/10/10 eMay dk JPO
7-
eaMy dk laj{kk ifji=
o’kZ 10@2012&13 rFkk 2@2014&15
8-
E.Co. Rly dk JPO
Q.2 Is there any provision to perform GDR at crew
changing point?
Ans
:- ,slk dksbZ izkoa/kku ;k funsZ”k ugha gS fd jfuax Vsªu dk GDR Crew changing Point ij cukuk gS] D;ksafd mijksDr iz”u ds mRrj esa
ftrus mnkgj.k fn, x, gS mUgha ls Li’V gksrk gS fd Loading
/unloading LVs”ku ;k Non TXR Point LVs”ku ij
Invalid BPC okyh Vsªu dks D;h;j djus ds iwoZ LVs”ku ij GDR tkaWp dk izkoa/kku gSA
Q.3 If BPC invalid of a train at unloading point
/ station / siding, how many
distance train can be run with
GDR?
Ans :-
Unloading Point / Station/ Siding ij xkM+h dk BPC invalid gksus ij GDR cuk;h tk,xhA rRi”pkr TXR control ds funsZ”ku ij xkMh ifjpkyu ds fn”kk esa izFke TXR
Point ;k 250
to 300 km, tks Hkh igys
feys] ogkaW rd xkM+h tk,xh vkSjBPC cuokus gsrq xkM+h dk tkaWp djk;k tk,xkAblds fy, fuEu fyf[kr fu;e
,oa funsZ”k gSA
1- fnukad 31@07@01 ds jsyos cksMZ dk i=kad % 2000/
safety / (A&R)/19/35 ds ikjk 2(iii)
2- fnukad 6-5-2005 ds jsyos cksMZ dk i=kad % M(N)/2005/Train
examination dk ikjk& (Xi)
3- fnukad 28@07@2009 ds jsyos cksMZ dk i=kad % 2005/
safety / (A&R)/19/35 ds o vuqPNsn&
2 esa
4- GDR dk izk:Ik esa mYys[k
Q.4 In case of
loaded running train, If BPC
becomes invalid, what procedure
should be done to work the train for further Journey.
Ans :- ;fn yksMsM jfuax Vsªu dk BPC
jfuax ds nkSjku Invalid gksrk gS rks ml xkM+h dk GDR ugha cusxk] cfYd jsYos cksMZ }kjk cuk;k x;k BPC dk izk:Ik esa mYys[k funsZ”kkuqlkj SCOR dks lwfpr fd;k tk,xk vkSj TXR
controller }kjk fyf[kr mfpr funsZ”k ds vuqlkj ifjpkyu ds
fn”kk esa izFke TXR Point
rd xkM+h tk,xh
vkSj xkMh dk tkaWp djokrs gq, BPC
dks Revalid fd;k tk,xkA rRi”pkr gh xkM+h vkxs ifjpfyr fd;k tk,xkA mnkgj.k ds
fy,A
1- BPC esa gh funsZ”k mYys[k jgrk gS tks jsyos cksMZ }kjk cuk;k x;k gSA
Q.5 Is freight train can be loaded with invalid
BPC Rake?
Ans :- invalid BPC okys
Rake dks yksfMax djkus dk dksbZ funsZ”k ugha gSA vFkkZr
yksMhax ugh djuk gS]
blds fy, fuEu fyf[kr fu;e ,oa funsZ”k gSA
1- fnukad 29@31@01@2007 ds jsyos cksMZ dk i=kad %2005/
M(N)/51 / 13/ PT
2- fnukad 13@9@2012 ds jsyos cksMZ dk i=kad% 2012/
Safety/(DM)/BPC/7/10
3- fnukad 13@8@2014 ds jsyos cksMZ dk i=kad % D.O.No
2013/M(N)22/CC/Rake
4- fnukad 18@6@2015 ds jsyos cksMZ dk i=kad % 2013/
M(N)/951/22/CC Rake PT2
5- fnukad 14@8@2009 HQ.C.
Rly dk i=kad % M/79/C&W/ Policy.
Q.6 can train crews work the train with invalid
BPC?
Ans :- Invalid BPC okyh xkM+h dks pykus ds fy, Train crew vf/kd`r ugha gSA
tc rd fd fof/klxar TXR
Controller ls fyf[kr funsZ”k ugha fn;k tkrk gSA
mnkgj.k ds fy,A
1-
fnukad 25@5@2005
ds jsyos cksMZ dk i=kad % 98/M(N)/951/12
2-
BPC esa mYys[k funsZ”k tks jsYos cksMZ }kjk fn;k x;k gSA
3-
fnukad 14@08@2009
ds H.Q. C. Rly dk i=
4-
vtuh dk BPC esa mYys[k funsZ”k
Q.7 Is there any provision of loading in 3 days
grace pociod for P.M. Rake
and in 5 days grace preriod for CC Rake?
Ans :- 3/5 days ds grace period esa BPC
invalid gks tkrk gSA ;g Period flQZ
yksMsM d.Mh”ku esa xkMh dks
ifjpkfyr djus gsrq x.kRkO; LVs”ku rd tkus ds fy,
fn;k x;k gSA ;g Empty
Condition TXR Point/ Base depo tkus ds fy, gksrk gSA
1-
fnukad 10@4@2006
ds jsyos cksMZ dk i=kad % 2005/M(N)/951/13 ds ikjk&7
2-
fnukad 19@12@2006
ds jsyos cksMZ dk i=kad % 2005/M(N)/951/13
3-
fnukad 13@9@2012
ds jsyos cksMZ dk i=kad % 2012/safety/(DM)/BPC/7/10
4-
fnukad 24@7@2014
ds jsyos cksMZ dk i=kad % 2013/TT-1/27/19
5-
fnukad 18@6@2015
ds jsyos cksMZ dk i=kad% 2013/M(N)/951/22/CC/Rake/ PT-2
6-
fnukad 14@8@2009 H.Q.C
Rly dk i=kad:
M/79/C &W Policy.
Q.8 With invalid BPC, a train can be run in bypass
route/ chordline to avoid train
examination or throughyard which are
not nomination for examination?
Ans :-
Invalid BPC okyh xkMh dks bypass
rout/ chord line ls
By Pass djus dk
izko/kku
ugha gSA cfYd ,slk djus ls jsyos cksMZ euk fd;k gSA mnkgj.k ds fy,A
1- fnukad 6-5-2005 ds jsYos cksMZ dk i=kad% M(N)/2005/train
examination ds ikjk&XI
2- fnukad 7-4-2006 dk i=kad% 2005/M(N)C
51/13 dk ikjk&7
3- fnukad 14@8@2009 dk H.Q.C.Rly i=kad% M/79/C&W/
Policy
Q.9 Who is the
authority to allow/ permit the train with invalid BPC after
overshooling TXR Point / 300km or more
than 300 km?
Ans :- BPC esa mYys[k funsZ”k rFkk H.Q.C.Rly ds i= ds vuqlkj Sr.
DME ds vUrxrZ TXR
controller gh invalid
BPC okyh xkMh dks TXR
Point ;k 300km
overshoot gksus ij
vkxs
ds fy, vf/kd`r dj ldrk gS rFkk vkxs izFke TXR Point ij xkMh
dk tkaWp djokrs
gq,
BPC dks Revalid djk;sxkA mnkgj.k ds fy,A
1- BPC esa fyf[kr funsZ”kA
2- H.Q.C.Rly 14-08- 2009 dk i=
Q.10 If loging of KM is not available / incorreet
available in this condition what is
period
of validation of BPC?
Ans :- ,slh fLFkfr esa CC Rake
dk Validation flQZ 20 fnu dk gksrk gSA
mnkgj.k ds fy, jsyos cksMZ dk i=kad %&
1-
94/M(N)/ 951/57/vo/1-11/ PT-2,
d/.25/10/04
2-
2013/M(N)/951/51/25. Dt. 2.1.2014 dk ikjk 3-2 gSA
Q.11 If loading/ unloading of F.T. rake is 2 or more
than 2 rake perday in a station/
siding,
who check the load before starting the train.
Ans :- ,slh fLFkfr esa xkMZ ,oa yks-ik-ls GDR u cuokrs gq, TXR/C&W
Staff ls tkaWp
djkus
dk izko/kku gS tks SEC Rly esa yxk gSA mnkgj.k ds fy, A
1- fnukad 31-3-2005 ds js-cks-dk i=kad 99/TC/
FM/26/1 ds ikjk&4-4 C&W examination
2- fnukad 8-2-2006 ds js-cks-dk i=kad 2005/M(N)951/13 dk ikjk VI
,oa tipling ds fy, IV
3- fnukad 7-3-206 ds js-cksMZ dk i=kad 2005/M(N)951/13
.
;g Hkh tkuuk
pkfg,A
Ø
xkM+h dh BPC ds oS/k fLFkrh esa ,d ls vf/kd ckj]
yksMhax@vuyksfMax LVs”ku ij] GDR cu ldrh gSa ijarq BPC dh voS/k fLFkrh esa ,d gh ckj GDR cuk;k tk;xkA
Ø
voS/kk BPC dh GDR cukrs gq, BPC dks revalid ugh fd;k tkrk gSA
Ø
voS/k BPCdh xkMh dk ifjpkyuSPAD tSlk lkadsfrd nq?kZVuk ds :Ik esa ekuk x;k
gSaA
Ø
voS/k BPC dh xkM+h dks chekj xkM+h ds :Ik esa ekuk x;k
gSA ;gh otg gS dh ,slh fLFkrh esa
yksfMax ds fy, izfrca/khr gSA
Ø
GDR tkaWp fjiksVZ gksrk gS u dh xkM+h dk
izek.ki=A
Ø
GDR tkWp ds
fy, jssyos cksMZ dksbZ le; dk fu/kkZj.k ugha fd;k gSA blfy, {ksf=;@eaMy Lrj esa
le; dk fu/kkZj.k djuk rdZ laxr ugha gSA
Ø
GDR & invalid BPC dk funsZ”k tks {ks=h;@eaMy Lrj ij fudysxk o
jsYkos cksMZ ds funsZ”kkuqlkj gh gksxkA
Ø
Train examination yard/ station esa 24
?kUVk ls vf/kd xkM+h dk LVscy jgus ij BPC voS/k gksxkA
Ø
Road side/wayside/ inroute station esa
LVscy yksaM] ftldk BPC oS/k gSa] mldk GDR ugh cusxkA